Point sur l'avancement


North Pennines AONB Geopark Progress Report 8

July 4, 2013

iGlass unit operational at Bowlees visitor centre! Conclusion of project. - En savoir plus >>>

North Pennines AONB Geopark Progress Report 7

April 3, 2013

Progress report for the period December 2012 - February 2013 - En savoir plus >>>

Rapport d'avancement des North Pennines AONB 6

December 12, 2012

Waiting for shipment of equipment - En savoir plus >>>

Rapport d'avancement des North Pennines AONB 5

September 10, 2012

Discussions with software developers. - En savoir plus >>>

Rapport d'avancement des North Pennines AONB 4

June 20, 2012

The progress diary from the North Pennines for the period 1 March - 31 May 2012 - En savoir plus >>>

Rapport d'avancement des North Pennines AONB 3

February 29, 2012

Développer l'unité numérique I-glass et son contenu. - En savoir plus >>>

Rapport d'avancement des North Pennines AONB 2

November 30, 2011

Attendre la confirmation du financement, ce qui signifie un léger retard du développement. - En savoir plus >>>

Rapport d'avancement des North Pennines AONB 1

September 3, 2011

Définir le projet en détail et obtenir l'accord pour le financement du projet. - En savoir plus >>>